Vnre.blogspot.com - According to Pham Thanh Binh, Deputy General Director of Thang Long Project Management under the Ministry of Transportation - Project owner, ring road 3 phase II, the first high roads of Hanoi started of construction, with total investment of over 5500 billion.
In the capital, loan capital of the Japan International Cooperation Agency (JICA) is principal.
Third ring road III phase II has a length of 8.9 km, from north Linh Dam to Mai Dich node; of which 8.5 km high viaduct. The road is built on high standard highway, located in the median strip between the ring road III phase 1, 28m wide, of which, on the high street's width is 24m. Average distance from the high street down the road on phase I is 8m.
As expected, this work will be completed within 30 months of construction.
Ring road III project includes three packages, of which, third package, built the first 3.3 km long from Thanh Xuan node to the Dai Tu bridge by the Thang Long General Construction Company, Civil Engineering Construction Corporation No.4 and Civil Engineering Construction Corporation No.8 undertaken.
The two remaining packages are first package starting at Mai Dich intersections to intersections Trung Hoa , the construction is expected to last year 2011, and the second package from Trung Hoa node to Thanh Xuan node.
Reported by Uong Lam/ VNA